19 August 2020 / Quality Alert

Metal Fire Door Frames & Doors

Metal fire door frames are a tested system so it’s critical each frame is manufactured to meet the requirements of the fire test to remain compliant.

Relevant Standard / AS 1905.1-2015

Components for the protection of openings in fire-resistant walls

Part 1: Fire-resistant doorsets

Key Elements

There are several key elements that need to be monitored in respect to the manufacture and install in accordance with each manufacturer’s test reports / construction manual.


Test reportIt is important to have the test report for the system. Request it when letting the contract
Metal thicknessRefer test report – usually 1.1mm min thickness but may be greater
Door stopMin 25mm as per the standard
Fixing points / strapsTypically 300mm maximum between fixings
Monitor closely as it has become an issue with manufacturers increasing spacings creating a likely non-confirming product. Refer photos below
P1240863.JPG

asdf

asdfsdf

P1240865.JPG

Insulation

Grout filled, prefilled insulation or site plasterboard backed dependant on what the frame is being fixed to and strictly as per the tested system details (no expander foam or the like)

Frame install

Frames installed square/plumb/not twisted

Clearances

Doors installed with max 3mm gaps to the jambs and head

Doors installed with max 20mm under door to floor substrate and 10mm floor covering across full width of the door

Metal hardware fixing plates (in fire doors)

Doors have metal plates to locate the door furniture

Check the door has a small hole drilled in the top on the hinge side. If the hole is there, then the door is installed the right way up.

If there is no hole in this location, then the door is likely installed upside down or back to front. Reinstall the door correctly or replace as required

Screws

All screws in hinges MUST be compatible metals, e.g. NO zinc screws in stainless steel hinges. Refer image below

Tag

Door frames and doors to have correct labels as per AS 1905.1 clause 6.1.4 (must include year of manufacture). Refer image below

Other considerations

In addition to the key elements, consider sensible door/door frame quality, including:


External doors frames requiring weather protection (hoods or the like)

Door frames preferably should not be ‘buried’ in wet area bedding or concrete (where this occurs the frame must be suitably prepared with metal primer and waterproofed)

Use stainless, epoxy painted or galvanised frames in corrosive environments. Use stainless within 100m of salt water

Utilise bat wing seals to provide a seal between airconditioned and humid external air in corrosive environments. This reduces saltwater forming on the frame

Jambs and head MUST be back filled in accordance with manufacturer’s details

All doors MUST be painted top and bottom

Ensure owner’s manuals have clear instructions on cleaning the doors/frames to avoid corrosion

Ensure owner’s manuals have information on the tested system door clearances (to avoid maintenance companies defecting doors against incorrect information post completion)


More information

Please contact the Quality Team if you have any questions

Phone 1300 HUTCHIES

Email QualityTeam@hutchies.com.au

Other Recent Activities

View all activities
HB-TryATrade-Lagoon-4-LowRes-.jpg
24 March / Training

This qualification applies to individuals working in, or wishing to transition into, a work health and safety (WHS) role who provide a broad range of technical knowledge and skills and have some limited responsibility for the output of others.

The qualification applies to those working as supervisors, WHS personnel, and workers in other WHS-related roles who manage risks effectively, apply relevant WHS laws, and contribute to WHS within the workplace in known or changing contexts with established parameters.

The specific nature of this course will include contextualisation of Hutchies’ Policies, Processes, Procedures, and Systems relating to on-site hazard identification, risk assessment and hierarchy of control measures within the scope of its operations.

Units of competency for the Cert IV WHS that we will cover are:

  • BSBHWS412 Assist with workplace compliance with WHS Laws
  • BSBWHS413 Contribute to Implement & Maintenance of WHS Consultation & Participation Processes
  • BSBWHS414 Contribute to Risk Management
  • BSBWHS415 Contribute to implementing WHS Management Systems
  • BSBWHS416 Contribute to Workplace Incident Response
  • BSBWHS417 Assist with Managing WHS Implication of Return to Work
  • BSBWHS418 Assist with Managing WHS Compliance of Contractors
  • BSBWHS431 Develop Processes and Procedures for controlling Hazardous Chemicals in the workplace
  • BSBCMM411 Make a Presentation
  • BSBWRT411 Write Complex Documents

Funding is available for eligible Queensland participants via CSQ.

For course inquiries call / email Warren Belford on 0427 337 379.

View More
22 March / Event

Please join us for a night of celebration to recognise Hutchies’ brightest learners 

Every year we identify an exceptional apprentices, cadets and continuous learners from Hutchies’ training and professional development programs.

Date and Time

Saturday, 22 March 2025
5.30pm for 6pm start

Location

Western Districts Rugby Football Club
65 Sylvan Road
Toowong QLD 4066
view map

Enquiries

Michelle Buckland
0447 758 566
training@hutchinsonbuilders.com.au

RSVP

Places are limited - please confirm
your spot by
Friday, 14 March 2025

View More
3 - 8 March / Weather Alert

With the threat of Tropical Cyclone Alfred tracking towards SEQ and forecast to make landfall from Thursday onwards, it is extremely important that we prepare our projects the best we can.

If all projects between Bundaberg and Byron Bay could today start the process of storm / cyclone preparations. 

This should be completed and documented using the Inspections > Site Shut Down - Cyclone Preparation Checklist F-084-C tab located on HammerTech.

Please note, any project that has an erected tower crane will also need to ensure they have updated documented advice from their crane engineer outlining the correct weathervane radius, this should be specific to your project. 

Hutchies' owned and managed cranes can coordinate this through Bradley Beck, all third party supplied cranes will need to actioned with their nominated representatives.

Any questions please call Jimmy Andersen on 0400 220 381 to discuss.

View More
HTA-2024-Brand-Graphics-04.jpg
11 Feb - 1 Mar / General

Calling all nominations for stand out apprentices, cadets and continuous learners across Hutchies.

Help us by nominating people you think are a true representation of Hutchies' way.

Nominate by COB Friday, 28 February 2025

View More
Graphics-06.jpg
10 February / General

Do you have a voice for radio? We're looking for 2 people to be the voices to Hutchies. 

Your voice could be featured in Hutchies' videos. 

And you could win an iPhone 16.

View More