1 March 2021 / Notice

Queensland Codes of Practice Updates

Workplace Health and Safety Queensland (WHSQ) has reviewed 21 Codes of Practice in line with regulator review period requirements.

WHSQ has communicated that the review was limited to technical accuracy, usability, and readability. The content has not been fully reviewed at this stage. Additional reviews of the updated codes will likely be undertaken soon, and notification will be communicated to all.

These updated Codes of Practice take effect 1 March 2021.

Action

All Queensland projects are required to update the following safety documentation to reflect the changes:

  • Project Risk Assessment (PRA)
  • Safe Work Method Statements (SWMS)

Key HSE documentation to be updated

Other Recent Activities

View all activities
9 April / Meetings

Thanks for participating in Hutchies' All Company Update.

A copy of the presentation slides is available to download below.

View More
HB-CO-IntCom-Campaign-2025-Graphic-WHSMP-V16-1-LowRes-.jpg
31 March / Update

All construction projects over $250K need a site-specific WHS Management Plan to ensure processes are in place to reduce health and safety risks.

The WHS Management Plan has been updated to align with Safe Work Australia's Model Code of Practice: Construction work.

The language has been refined to be clearer about the legal and other requirements that must be followed on site.

Actions

Projects with more than 3 months left must update the WHSMP and appendices by 30 April 2025.

Projects with less than 3 months should review the amendment register and make any relevant updates to the current plan.

Team HSE Managers

  • Coordinate the update of the plan and all appendix documents in consultation with the project team
  • Ensure proper archiving of superseded plans (2 years following project completion)

Project Manager

  • Ensure plans are updated within the 3 month period and approved for use

Project Teams

  • Update the WHS Management Plan with the Team HSE Manager
  • Communicate the update to subcontractors 
  • Maintain updated hard copy of WHS Management Plan on site 

Team Leaders 

  • Where the team does not have a Team HSE Manager, the Team Leader is required to oversee this process and all updates

Further updates

The following guidance material has also been updated. A full list of amendments can be found here.

View More